BOARD OF EDUCATION
REGULAR MEETING / Public Hearing (District Health & Safety)
Tuesday, August 24, 2021 – Crispell Middle School
ADDITION TO THE AGENDA
Recommend the Board of Education approve the following addition to the Agenda:
CPL and the Pike Company, the District’s Architect and Construction Manager for the 2019 Capital Improvement Project – Phase II, recommend the Board of Education to approve the following Change Orders. All to be financed through the Construction Contingency and/or Prime Contractor Allowance.
No. Description Contractor Increase Cost
Pine Bush High School SED No: 44-04-01-06-0-007-027
- 003 RFI 39 – Demo Weight Room HVAC $ 4,100.18
- 017 RFI 44 – Corridor C110 Steel Reinforcement General $ 2,575.45
- 028 RFI 29 – Haas Center New Flooring General $48,885.13
- 051 RFI 76 – Fitness Center Roof Leader General $ 2,120.71
- 054 IB 08 – Haas Center Flooring Patch and Door Frames General $ 8,841.34
- 057 IB 07 – Haas Corridor Ceiling General $ 5,096.58
- 068 IB 14 – Wall at Home & Careers Rm General $ 9,835.20
- 082 RFI 64 – Security Vestibule Window General $ 2,608.42
Pakanasink Elementary School SED No: 44-04-01-06-0-012-0015
- 007 RFI 9 – Pool Room Door Opening General $ 4,060.45
- 027 RFI 48 – Nonfunctioning valves Plumbing $ 3,559.67
- RFI 51 – No Branch Valves
- 023 RFI 60 – Boys and Girls Locker Coils HVAC $ 2,203.00
- 024 RFI 65 – Security Return Air HVAC $ 2,050.08
- 026 RFI 69 – Reuse Existing WC Carriers Plumbing $ 6,805.32
- 031 RFI 49 – PAK Bathrooms HVAC $12,708.00
- 055 RFI 77 – Locker Grills HVAC $ 281.14
- 081 RFI 97 – Entrance Sidewalk Site $16,748.00
- 083 RFI 100 – Security Vestibule Wall Finish General $ 3,634.53
- 089 RFI 104 – Tremco Roofing General $16,114.16
Circleville Middle School SED No: 44-04-01-06-0-014-015
- 011 RFI 16 – Locker Room Ceiling Paint General $ 9,647.00
- 012 RFI 21 – Footing Elevation General $ 2,639.59
- 035 RFI 56 – CVMS EF-8 HVAC $ 6,439.00
- 088 RFI 105 – Tremco Canopy Roof General $17,919.29
Circleville Elementary School SED No: 44-04-01-06-0-009-016
- 016 Boiler Pumps HVAC $ 6,600.00
Total Change Orders by Contract:
Starting Balance Total Changes Adjusted Balance
- General $6,442,100.00 $133,974.85 $6,576,074.85
- HVAC $3,877,000.00 $ 34,381.40 $3,911,381.40
- Plumbing $ 895,000.00 $ 10,364.99 $ 905,364.99
- Site $4,950,000.00 $ 16,748.00 $4,966,748.00