Student Registration     Stay Connected with ParentSquare

Whom to Contact and When      Access Your Student’s Gmail Account

Facilities Modernization Project Totals by Building

Below are the totals for each school for the proposed $76.7 million facilities modernization project being voted on by residents on Thursday, Dec. 6, 2018. Click on an individual school to see the list of all projects included for that building listed in two categories: outstanding issues and new investments.

Circleville Elementary           $4,579,646

EJ Russell Elementary           $7,579,288

Pakanasink Elementary       $6,471,232

Pine Bush Elementary          $7,201,929

Circleville Middle School     $15,059,894

Crispell Middle School          $5,320,755

Pine Bush High School         $30,486,907

District-Wide Total                $76,699,651

 

Building Condition Survey/Outstanding Issues $58,526,477

New Investments                                                              $18,173,174

District-Wide Total                                                            $76,699,651

Circleville Elementary School

Building Condition Survey/Outstanding Issues  $4,363,646

  • Remediate Floor Cracks on 2nd Floor of North wing
  • Repoint Brick Façade in Select Locations
  • Replace Non-Insulated Exterior Doors
  • Replace Flooring in Select Areas (Haz Mat Abatement Required)
  • Replace Ceilings in Select Areas (Haz Mat Abatement Required)
  • Replace Outdated Interior Doors Where Necessary
  • Provide Missing Fascia/Wall Panel at Northeast Corner of Building
  • Replace Windows in Select Areas
  • Remove Outdated Rooftop Equipment
  • Replace Damaged Skylights Where Necessary
  • Replace Door Lock Cores to Provide Unified Keying System (District-Wide)
  • Address Roof Framing Structural Issues
  • Replace Boilers
  • Replace Fuel Oil Pumping System
  • Provide Relief Air Path In Select Areas
  • Provide Ground Fault Interrupter Protection at Required Locations
  • Replace Outdated Power Panels & Feed Conductors Throughout Building
  • Replace Existing Circuitry Serving Flood Light Fixture
  • Provide Lamp Shatter Shields for Lighting Fixtures with Exposed Lamps
  • Replace Entrance of Electrical Service
  • Provide Fire Alarm Strobes at Required Locations
  • Replace Interior Emergency Lighting & Provide Additional Where Required
  • Install Smoke Detection Devices Where Required
  • Reconstruct & Repave Parking Lots with New Traffic Flow Pattern
  • Provide Ramp or Stair Lift to Cafetorium Stage (ADA Upgrade)
  • Provide Code Compliant Access to Rescue Window in Special Ed. Classroom
  • Replace Air Handling Unit in Nurse Suite
  • Provide New Sound System at Cafetorium Stage
  • Replace Air Handling Unit in Gymnasium
  • Provide More Parking
  • Address Damaged Folding Partition Wall in Gymnasium

New Investments $216,000

  • Security Vestibule at Main Entrance
  • Upgrade Athletic Field for Modified Sports

Circleville Elementary School Building Total: $4,579,646

Return to top

Edward J. Russell Elementary School

Building Condition Survey/Outstanding Issues $7,023,448

  • Provide Sprinkler System in Basement Storage Area
  • Remediate Mildew and/or Moss at Brick Façade Areas
  • Replace Handrails (ADA Upgrade) & Expansion Joint at Kitchen Entrance
  • Replace Damaged Downspouts Where Necessary
  • Replace Door Lock Cores to Provide Unified Keying System (District-Wide)
  • Replace Ceilings in Select Areas (Haz Mat Abatement Required)
  • Replace Flooring in Select Areas (Haz Mat Abatement Required)
  • Refinish Gymnasium Floor
  • Replace Folding Doors in Gymnasium
  • Paint Gymnasium
  • Replace Air Handling Units in Gymnasium
  • Replace Air Handling Unit in Kitchen
  • Replace Outdated Power Panels
  • Provide Ground Fault Interrupter Protection at Required Locations
  • Provide Fire Alarm Strobes at Required Locations
  • Provide Additional Emergency Egress Lighting at Required Locations
  • Replace Exit Lighting (LED Upgrade)
  • Provide Locks for Electrical Panels in Corridors
  • Provide New Sound System at Cafetorium Stage
  • Replace Hot Water Heaters
  • Reconstruct & Repave Parking Lots with New Traffic Flow Pattern
  • Provide Fencing Around Exterior Propane Tank
  • Reconstruct Sidewalks Where Necessary
  • Provide Grading & Fencing for Athletic Fields & Playground
  • Address Structural Integrity of Rope/Cargo Net Activities in Gymnasium
  • Replace Windows in Select Areas
  • Provide A/C & Ventilation to Main Office
  • Replace Outdated Split Systems

New Investments $555,840

  • Security Vestibule at Main Entrance
  • Provide Access to Athletic Fields
  • Relocate Soccer Field
  • Provide New Scoreboard
  • Provide Bullpen Area for Baseball Field
  • Provide Irrigation at Athletic Fields
  • Provide Dedicated Serving Line in Cafeteria

EJR Elementary School Building $7,579,288

Return to top

Pakanasink Elementary School

Building Condition Survey/Outstanding Issues               $6,363,232                                                                                                                                   

  • Replace Fascia Panels & Reseal Control Joints (Haz Mat Abatement Required)
  • Replace Non-Insulated Exterior Doors
  • Replace Windows in Select Areas
  • Replace Portion of Roofing
  • Replace Flooring in Select Areas
  • Replace Ceilings in Select Areas
  • Provide ADA Compliant Hardware & Replace Wire Glass at Main Office
  • Provide Fire Caulk at Thru-Wall & Thru-Floor Penetrations
  • Address Roof Framing Structural Issues
  • Replace Damaged Exterior Overhead Doors
  • Replace Door Lock Cores to Provide Unified Keying System (District-Wide)
  • Remediate Water Infiltration from Courtyard
  • Provide Relief Air Path In Select Areas
  • Replace Relief Air Path In Select Areas
  • Provide Supplemental Heating in K-1-2 Wing
  • Replace Air Handling Units in Main Office
  • Provide Ventilation in Office Area Suites
  • Provide Ground Fault Interrupter Protection at Required Locations
  • Replace Outdated Power Panels & Feed Conductors Throughout Building
  • Provide Lamp Shatter Shields for Lighting Fixtures with Exposed Lamps
  • Provide Fire Alarm Strobes at Required Locations
  • Provide Additional Emergency Egress Lighting at Required Locations
  • Upgrade Fire Alarm System
  • Reconstruct & Repave Parking Lots with New Traffic Flow Pattern
  • Reconstruct & Repave Asphalt Playground Area
  • Clean & Inspect Underground Water Storage Tank
  • Replace Pool Heat Exchanger
  • Replace Damaged Tile at Pool
  • Replace Air Handling Units in Gymnasium
  • Renovate Boys & Girls Locker Rooms
  • Provide Lift to Pool (ADA Upgrade)
  • Provide New Permanent Walls at Existing Partition Walls
  • Renovate Boys & Girls Bathrooms in Main Corridor
  • Renovate Boys & Girls Bathrooms Adjacent to Main Entrance
  • Fill in Former Exterior Louvers Locations with Like Construction
  • Renovate Small Dual Bathrooms (Accessible from Classrooms)

New Investments  $108,000

  • Security Vestibule at Main Entrance

Pakanasink Elementary School Building Total: $6,471,232

Return to top

Pine Bush Elementary School

Building Condition Survey/Outstanding Issues   $5,236,329

  • Repoint Brick Façade in Select Locations
  • Provide New Gliders on Rescue Windows
  • Replace Damaged Downspouts Where Necessary
  • Provide New Flooring & Wall Base in Kitchen
  • Replace Door Lock Cores to Provide Unified Keying System (District-Wide)
  • Replace Windows in Select Areas
  • Provide Air Conditioning to 2nd Floor Classrooms
  • Replace Unit Ventilators (with A/C Capacity) on 1st Floor Classrooms
  • Provide Ground Fault Interrupter Protection at Required Locations
  • Provide Lamp Shatter Shields for Lighting Fixtures with Exposed Lamps
  • Provide Fire Alarm Strobes at Required Locations
  • Provide Additional Emergency Egress Lighting at Required Locations
  • Replace Exit Lighting (LED Upgrade)
  • Upgrade Plumbing fixtures to the Auto Style Flush Valves
  • Provide Fencing Around Exterior Propane Tank
  • Remediate Storm Water Drainage Issues
  • Raise Window Sills in Cafeteria (Security & Drainage Upgrade)
  • Provide Upper Casework in Classrooms
  • Address Structural Integrity of Rope/Cargo Net Activities in Gymnasium
  • Provide Building-Wide Generator
  • Provide New Gymnasium Wall Padding
  • Provide Vertical Exterior Expansion Joint Filler In Select Areas
  • Scrape, Prime & Paint Lintels in Select Areas
  • Clean & Patch Masonry Window Sills & Headers
  • Replace Damaged Glass Block Windows
  • Patch & Paint Damaged Ceiling Areas
  • Replace Flooring & Provide Painting at 1st Floor Corridor
  • Replace Ceilings in Select Areas
  • Replace Boilers
  • Reconstruct & Repave Parking Lots Where Necessary

New Investments $1,965,600

  • Security Vestibule at Main Entrance
  • Provide Athletic Field Bathroom Facility (Separate Building)
  • Redesign & Provide Additional Athletic Fields (Including Irrigation)

Pine Bush Elementary School Building Total $7,201,929

Return to top

Circleville Middle School

Building Condition Survey/Outstanding Issues  $11,574,000

  • Address Minor Damage at Base of Columns
  • Patch Cracks in Select Flooring Areas
  • Repoint Brick Façade in Select Locations
  • Repoint Chimney Cap
  • Replace Exterior Doors in Select Areas
  • Replace Windows in Select Areas
  • Replace Portion of Roofing
  • Provide ADA Compliant Hardware & Replace Wire Glass Where Necessary
  • Address Roof Framing Structural Issues
  • Provide Fire Proofing for Structure at Basement Storage Area
  • Replace Lower Exterior Soffits at Stairwells
  • Scrape, Prime & Paint Handrails at Ramp
  • Replace Missing Window Sill at Boiler Room
  • Renovate Faculty Bathrooms
  • Provide Fire Caulk at Thru-Wall & Thru-Floor Penetrations
  • Renovate Boys & Girls Bathrooms
  • Replace Boilers
  • Provide Exhaust Fan System Where Necessary
  • Provide Air Conditioning to Offices Where Necessary
  • Replace Air Handling Units in Select Classrooms
  • Replace Exhaust/Relief Fans on Roof Where Necessary
  • Replace Unit Ventilators Where Necessary
  • Replace Entrance of Electrical Service
  • Provide Ground Fault Interrupter Protection at Required Locations
  • Replace Outdated Switchboards With New Main Distribution Panel
  • Replace Outdated Power Panels & Feed Conductors Throughout Building
  • Provide Lamp Shatter Shields for Lighting Fixtures with Exposed Lamps
  • Provide Additional Emergency Egress Lighting at Required Locations
  • Upgrade Fire Alarm System
  • Upgrade Plumbing fixtures to the Auto Style Flush Valves
  • Reconstruct & Repave Parking Lots with New Traffic Flow Pattern
  • Provide Additional Parking
  • Provide Grading & Drainage at Athletic Fields
  • Patch & Refinish Tech Shop Flooring
  • Replace Air Handling Unit in Cafeteria
  • Renovate Art Room
  • Renovate Family & Consumer Science Classroom
  • Replace Door Lock Cores to Provide Unified Keying System (District-Wide)
  • Address Air Handling Unit Leak in Gymnasium
  • Renovate Boys & Girls Locker Rooms
  • Provide Grading & Drainage at Athletic Fields
  • Replace Backstop
  • Replace Home & Away Bleachers
  • Replace Ceilings in Select Areas (Haz Mat Abatement Required)
  • Update Elevator
  • Provide Vertical Exterior Expansion Joint Filler In Select Areas
  • Renovate Loading Dock
  • Install Exhaust Fans Where Necessary
  • Provide New Work Tables in Tech Classroom (Including Lockers Below Table)

New Investments  $3,485,894

  • Security Vestibule at Main Entrance
  • New Grass Athletic Field w/ 6 Lane Track, Lighting & Jumping/Throwing Areas

Circleville Middle School Building Total: $15,059,894

Return to top

Crispell Middle School

Building Condition Survey/Outstanding Issues  $4,931,955

  • Reconstruct Foundation Wall at South Façade
  • Repoint Brick Façade in Select Locations
  • Replace Exterior Insulated Metal Wall Panels Where Necessary
  • Replace Ceilings in Select Areas (Haz Mat Abatement Required)
  • Provide Gates at Open Exterior Stairwells
  • Replace Door Lock Cores to Provide Unified Keying System (District-Wide)
  • Renovate Select Bathrooms (ADA Upgrades)
  • Revise Relief Air Path In Select Areas
  • Provide Relief Air Path In Select Areas
  • Provide Ventilation in Select Areas
  • Upgrade Exterior Louvers for Unit Ventilators
  • Replace Convectors Throughout Building
  • Provide Ground Fault Interrupter Protection at Required Locations
  • Replace Outdated Power Panels & Feed Conductors Throughout Building
  • Provide Fire Alarm Strobes at Required Locations
  • Provide Additional Emergency Egress Lighting at Required Locations
  • Provide Lamp Shatter Shields for Lighting Fixtures with Exposed Lamps
  • Upgrade Plumbing fixtures to the Auto Style Flush Valves
  • Replace Catch Basins in Select Areas
  • Replace Fencing Where Necessary
  • Reconstruct & Repave Parking Lots with New Traffic Flow Pattern
  • Replace Lockers Where Necessary
  • Provide Acoustical Upgrades in Tech Building
  • Replace Air Handling Units in Gymnasium
  • Renovate Boys & Girls Locker Rooms
  • Refinish Gymnasium Floor
  • Replace Backstop
  • Replace Home & Away Bleachers
  • Paint Gymnasium
  • New Backboards in Gymnasium
  • Replace Fencing at Athletic Fields
  • Replace Flooring in Select Areas (Haz Mat Abatement Required)
  • Replace Bathroom Tile in Select Areas
  • Replace Outdated Interior Doors Where Necessary
  • Renovate Loading Dock Canopy
  • Update Custodial Closets Where Necessary
  • Address Heating/AC in Office/Principal area
  • Replace Drinking Fountains Where Necessary
  • Replace Damaged Panels in Select Folding Partitions
  • Replace Carpet Where Necessary
  • Replace Flooring in Tech Building
  • Replace Stage Lighting

New Investments $388,800

  •  Security vestibule at Main Entrance (Including ADA Access)
  • Provide New Scoreboard

Crispell Middle School Building Total  $5,320,755

Return to top

Pine Bush High School

Building Condition Survey/Outstanding Issues  $19,033,867

  • Replace Select Exterior Doors
  • Replace Windows in Select Areas
  • Replace Portion of Roofing
  • Provide Fire Caulk at Thru-Wall & Thru-Floor Penetrations
  • Replace Door Lock Cores to Provide Unified Keying System (District-Wide)
  • Renovate Select Bathrooms
  • Replace Outdated Interior Doors Where Necessary
  • Remediate Leaks in Select Areas
  • Provide Gas Emergency-off Buttons & Associated Valves
  • Provide Ventilation to Select Rooms
  • Provide Ventilation Upgrades in Admin Wing
  • Replace Outdated Unit Ventilators in Select Areas
  • Provide Larger “Emergency Power Off” Signage at Existing Locations
  • Provide Ground Fault Interrupter Protection at Required Locations
  • Provide Lamp Shatter Shields for Lighting Fixtures with Exposed Lamps
  • Provide Shut Off Valve & Locking Emergency Push Button in Select Rooms
  • Provide Additional Emergency Egress Lighting at Required Locations
  • Replace Exit Lighting (LED Upgrade)
  • Provide Fire Alarm Strobes at Required Locations
  • Replace Hot Water Heater
  • Provide Emergency Eye Wash Station in Boiler Room
  • Replace Custodial Closet Faucets
  • Reconstruct & Repave Parking Lots with New Traffic Flow Pattern
  • Reconstruct Sidewalks Where Necessary
  • Provide Fencing Around Exterior Propane Tank
  • Replace Lockers Where Necessary
  • Replace Stage Theatrical Lighting Fixtures
  • Replace Stage Work Lighting Fixtures
  • Replace Master Clock System in its Entirety
  • Provide Electronic Push Door Controllers Where Necessary (ADA Upgrade)
  • Replace Walk-In Freezers & Refrigerators
  • Replace Building Wide Generators
  • Provide Acoustical Treatment in Band Room & Auditorium
  • Replace Stage Dimmer Rack
  • Provide Exterior Walking Path Lighting
  • Relocate Counseling Suite across from Main Office
  • Relocate School Offices Where Necessary
  • Remove Exterior Ropes Course
  • Upgrade Fencing & Lighting at Tennis Courts
  • Provide Additional Filtration Pump at Pool
  • Replace Pool HVAC System
  • Renovate Pool Locker Rooms (ADA Upgrade)
  • Provide Backup Pump into Existing Chlorination System at Pool
  • Replace Sink in Athletic Training Room
  • Renovate Boys & Girls Main Locker Rooms
  • Renovate Basement Team Locker Rooms
  • Provide Gate/Door to Gymnasium Folding Partition
  • Replace Flooring in Select Areas (Haz Mat Abatement Required)
  • Reconstruct Retaining Wall & Guardrail Fencing
  • Provide Vertical Exterior Expansion Joint Filler In Select Areas
  • Reconstruct Damaged Brick Façade & Brick Wing Wall at Pool Entrance
  • Repoint Brick Façade in Select Locations
  • Replace Ceilings in Select Areas
  • Provide Ventilation in Select Areas
  • Upgrade Plumbing fixtures to the Auto Style Flush Valves
  • Provide Storm Water Management Upgrades
  • Provide Additional Fencing in Select Locations
  • Replace Carpet in Select Areas
  • Replace Outdated Science Casework (Including Plumbing Fixtures)
  • Renovate Family & Consumer Science Rooms

New Investments $11,453,040

  • Security Vestibule at Main Entrance
  • Provide Wayfinding Signage Throughout Building
  • Renovate Library Center Reading Area (Including ADA Upgrades)
  • New Synthetic Turf Field
  • New 8 Lane Track
  • New Expanded Bleachers (Home & Away)
  • New Press Box
  • Concession Stand, Locker Rooms & Bathrooms Under Bleachers
  • New Scoreboard & Sound System
  • New Field Lighting
  • New Multi-Use Synthetic Turf Athletic Field
  • Provide New Fitness Center (Includes Weight Room Relocation)

PBHS Building Total $30,486,907 

Return to top

Pine Bush Central School District
State Route 302, Pine Bush, NY 12566
Phone: (845) 744-2031
Fax: (845) 744-6189
Amy Brockner
Interim Superintendent of Schools
This website is maintained by Public Information Specialist Linda Smith. It is the goal of the Pine Bush Central School District that this website is accessible to all users. View our accessibility statement. The district is not responsible for facts or opinions contained on any linked site. Some links and features on this site require the Adobe Acrobat Reader to view. Visit the Adobe website to download the free Acrobat Reader. This website was produced by Capital Region BOCES Engagement & Development Services, Albany, NY. Copyright © 2024. All rights reserved.